Project Details:

Commencement: September, 2018 Completion: November, 2018

Project involved the following:

Plumbtrax has been engaged by Mornington Shire Council to carry out Supply & installation of a new Pump station within the road reserve to mitigate neighbouring houses becoming flooded in heavy rain events, The works comprised of the following:

  • Installation of twin 225mm outlet pumps, pipe connections & check valves, backflow prevention devices
  • Installation of new pump wells 2.5m depth working within ocean tide conditions @ 1m depth, dewatering involved
  • Connections of 3 phase power
  • Re-instatement to road reserve
  • Drainage works, pit construction